Stoke Bardolph

Stoke Bardolph

Client: Morgan Sindall / National Grid

Job: Installation of new 400/132kV substation on greenfield site including:

  • Full ground remediation – Lime stabilisation
  • Two Supergrid transformers installed in moated bunds
  • Steel support structures and foundations for all AIS equipment
  • 1.5km Access Road
  • Amenity buildings and associated foundations and services
  • Security fencing access gates & foundations

Discuss your project with us today

Phone us on 01332 664747, email us at info@rclltd.com or use our online form.